The Project of Fluidal Block Construction in the Zofiówka CHP Speeds Up

The works on the construction of the CFB70 block, i.e. the largest investment of the JSW Group’s Spółka Energetyczna Jastrzębie, have gathered pace. Such acceleration was necessary to ensure that a new fluidal bed can work at the Zofiówka CHP by the end of 2015.

On 9 December, following an agreement with the technical advisor, another agreement was concluded by Spółka Energetyczna Jastrzębie S.A., i.e. an agreement with the Commercial and Legal Advisor (the consortium of EM&CA and Kancelaria Radcy Prawnego – Małgorzata Szychowska Łódź law firm). The agreements with the advisors make it possible to effectively continue the implementation of the company’s most important investment – the construction of CFB 70MWe fluidal block.

In accordance with the agreement, the commercial and legal advisor is responsible for specifying favourable and lawful provisions to be included in the documentation required in the tender procedure for selection of the General Contractor, as well as ensuring that a utilities contract notice be prepared and duly issued. The commercial and legal advisor will also be actively involved in the entire process of selecting the General Contractor, and will give advice on specifying suitable business solutions and addressing legal and business risks in the contract with the selected General Contractor.

To remind: on 21 October, SEJ already entered into an agreement with ILF Consulting Engineers Polska which has become the company's technical advisor. ILF, in turn, has established cooperation with Energoprojekt Katowice, which has become the project’s subcontractor. “Representatives of both companies are currently carrying out on-site inspections on the premises of SEJ,” says Zbigniew Opałko, project manager of the fluidal block construction. “Detailed analysis of the existing documentation and examination of the facilities located within the plant’s area, will soon make it possible to create, among other things, a construction design, and will also allow us to obtain all necessary building permits and permits for subsequent operation of the block. Until now, ILF has already prepared the wording of a technical part to be contained in the contract notice for the selection of the general contractor,” adds Zbigniew Opałko.

Next year in January, SEJ will launch the public tender for the selection of the General Contractor. The Management Board of SEJ foresees that given the complexity and size of the project, the process of selecting the General Contractor will take at least a few months.

“We expect that we will obtain a final and binding building permit in the middle of the next year, and at the end of the year, the agreement with the General Contractor will be signed,” says the project manager.

The expected date of commencing construction works is scheduled for March 2013. The new fluidal block which will blend with the existing infrastructure, will have been completed by the end of 2015.

Other news

PBSz strengthens its position - annex to the agreement will provide more revenue

Przedsiębiorstwo Budowy Szybów, a JSW Group company, has entered into an annex to the agreement with KGHM Polska Miedź S.A. dated 20 December 2021 concerning the execution of roadway excavations, mining works and provision of technical infrastructure securing the…

Coking coal and coke - foundation of green transition

Jolanta Gruszka, Vice-President of the JSW SA Management Board for Sales, participated in a conference on, among other things, the development of wind energy in Poland. During her speech at the panel discussion, she stressed the importance of coking coal and coke in the…

JSW: more months with production and sales above plan

Jastrzębska Spółka Węglowa has published the assumptions of the JSW Group's Technical and Economic Plan (TEP) for 2025. According to the assumptions, coal production this year is expected to reach 13.37 million tons, including 11.35 million tons of coking coal. Coke…

Cyber security in mining - CyberRange2025

JSW is hosting the nationwide CyberRange conference - Industrial Defense League 2025 - an event of strategic importance for the digital transformation of mining. Jastrzębska Spółka Węglowa is represented by Adam Rozmus, Vice-President of the JSW Management Board for…

Concert in memory of mining disaster victims

A concert commemorating miners who lost their lives underground in disasters was held at the NOSPR Chamber Hall in Katowice. The event also aimed to express gratitude to all those who support the families of victims and those injured in mining accidents.

JSW Group’s Q1 results

JSW Group closed the first quarter of 2025 recording a net loss of PLN 1.36 billion. The result was very significantly affected by the recognition of an impairment loss on non-financial non-current assets in the amount of PLN 648 million, related to the January fire at…

More news