Opening of a new plant

Przedsiębiorstwo Gospodarki Wodnej i Rekultywacji built a modern greenfield plant for production of cement and mineral grouts for JSW mines over only 8 months. The plant was built in Czerwionka-Leszczyny on a site owned by PGWiR, a JSW Group company.

photo. Mateusz Paszek

– The eight months from the construction decision to today’s opening is a record-breaking time, but quite typical of JSW and this strategic investment project. Today’s grout market is characterized by high quality and price diversification. Thanks to the project JSW’s mines will receive deliveries that guarantee consistency and compliance with the expected technical requirements and parameters of the grouts, combined with full control and influence over their quality. In addition, their price will be stable and reasonable, and all this will have influence on the “Efficiency” Program run in the company, said Artur Dyczko, acting President of the JSW SA Management Board.

The project is worth PLN 3.5 million net. In addition to modern warehouses, the plant has a modern, automated production line that can be operated by only two employees. The production capacity of the installation allows for production of 15 thousand tons of grout per year in a single-shift system, hence the plant is able to meet the demand of JSW’s mines.

– The plant offers universal capacities supporting production of grouts based on cement, fly ash and aggregates of different fractions. This makes it possible, depending on the formula used, to produce grouts for mechanical lining, ordinary and reinforced shortcrete, and grouts for construction of dams and plugs, said Jan Przywara, President of the PGWiR SA Management Board, at the opening ceremony.


Other news

Coking coal at the center of industrial transition

During the 17th European Economic Congress in Katowice, Adam Rozmus, Vice-President of the JSW Management Board for Technical and Operational Matters, spoke in a debate on the future of the mining industry. Panelists discussed, among other things, the place of coking…

Shaft sinking completed at Zofiówka

The sinking of shaft IIz to a depth of 1,104.68 meters has been completed at the Borynia-Zofiówka-Bzie mine in the Zofiówka Section. This is a very important project for the mine from the point of view of building the new 1,080 level.

Polish Cup returns to JSW Jastrzębski Węgiel

After a 15-year hiatus, the volleyball players once again took the TAURON Polish Cup, defeating Aluron CMC Warta Zawiercie 3:1 in the final in Kraków. After the great success, the team appeared with the trophy at the headquarters of JSW, the title sponsor, where they…

JSW SA has applied to the Ministry of Climate and Environment for a refund of the windfall tax

On Friday, 11 April 2025, JSW SA requested a refund of the windfall tax of PLN 1.6 billion paid in 2023 and surcharged in 2024. This is the result of a thorough analysis of the regulations that imposed the obligation to pay this levy on the Company.

Budryk Mine hosted the best students of mining schools

Promoting a culture of safety among young people, educating about labor law and OHS principles, as well as drawing attention to the importance of mining for the region and the economy - these are the main goals of the competition entitled "Safe Step to Mining with OHS",…

New longwalls in Pniówek mine

Two new longwalls with total reserves of approx. 1.4 million tons of coking coal with very good parameters have been put into operation at the Pniówek mine.