Ikona BIP Ikona Portal Pracownika Ikona poczty Facebook Twitter Instagram Youtube Linkedin RSS Ikona szukania PLEN

The most difficult stage of deepening shaft III at KWK Pniówek has been completed

Work on the deepening of the material transport shaft at the Pniówek mine has reached a key stage. Shaft III has been deepened to the target depth of 1,053 meters. The implementation of the project is an important step in the modernization of the mine's infrastructure, providing new development opportunities and improving working conditions.

photos: Dawid Lach

Deepening of the shaft from a depth of 865.3 meters began in July 2020 after completion of preparatory works. As regards the deepening of Shaft III, 187.7 meters of the shaft in the final casing have been completed, along with one-sided inlets at the depths of 965.4 meters and 1,052 meters, and a two-sided inlet at the 1,000-meter level. 

- The investment will enable efficient transport of materials and workers to the 1,000m level, which will significantly improve logistics and ventilation of the pits - said Zbigniew Czarnecki, director of the KWK Pniówek mine.

On 19 November, a ceremony was held at the bottom of Shaft III, during which the mine director received official confirmation of the completion of the task. 

- This project, which has been ongoing for several years, was one of the most important tasks in Pniówek. The most difficult stage - deepening the shaft - has been completed, and work is currently underway to reinforce the shaft pipe on the deepened section - said Adam Rozmus, JSW's Vice-President for Technical and Operational Matters.

The project is being carried out by a consortium of companies: Przedsiębiorstwo Budowy Szybów from the JSW Group and PPG Row-Jas.
 

Other news

New Community Center with a fire station built thanks to the mine

After many years of problems with recurring damage to the building of the Krzyżowice Volunteer Fire Brigade, the firefighters have gained a modern headquarters and the residents a Community Center. The project was financed by the Pniówek mine as part of rectification of…

JSW met its production plan for 8 months of 2025

Jastrzębska Spółka Węglowa recapped the implementation of its Technical and Economic Plan for August 2025. Although the last month was difficult due to operational challenges in the coal segment, the Company successfully met its YTD production plan. The coke segment…

Another longwall at KWK Pniówek

The Pniówek mine has put into operation a new longwall, Pw-1, in seam 361. Its estimated reserves amount to nearly 490,000 tons of high quality type 35.1 coking coal.

Jastrzębie Agreement - a breakthrough in the fight for workers' rights

On 3 September 1980, one of the most important August Agreements - the Jastrzębie Agreement - was signed in Jastrzębie-Zdrój. It was a moment that changed Polish history forever, strengthening the struggle for workers' rights and becoming a symbol of opposition to…

New large longwall at Budryk

At the Budryk mine, the Bw-1 longwall in seam 405/2, with resources of more than 1.6 million tons of coking coal, has been put into operation.

Changes in the JSW Management Board

Today (1 September 2025) the JSW Supervisory Board decided to dismiss Remigiusz Krzyżanowski from his position as Vice-President of the Management Board for Financial Matters. At the same time, it seconded its member, Bogusław Oleksy, to temporarily perform the duties…

More news