Ikona BIP Ikona Portal Pracownika Ikona poczty Facebook Twitter Instagram Youtube Linkedin RSS Ikona szukania PLEN

The most difficult stage of deepening shaft III at KWK Pniówek has been completed

Work on the deepening of the material transport shaft at the Pniówek mine has reached a key stage. Shaft III has been deepened to the target depth of 1,053 meters. The implementation of the project is an important step in the modernization of the mine's infrastructure, providing new development opportunities and improving working conditions.

photos: Dawid Lach

Deepening of the shaft from a depth of 865.3 meters began in July 2020 after completion of preparatory works. As regards the deepening of Shaft III, 187.7 meters of the shaft in the final casing have been completed, along with one-sided inlets at the depths of 965.4 meters and 1,052 meters, and a two-sided inlet at the 1,000-meter level. 

- The investment will enable efficient transport of materials and workers to the 1,000m level, which will significantly improve logistics and ventilation of the pits - said Zbigniew Czarnecki, director of the KWK Pniówek mine.

On 19 November, a ceremony was held at the bottom of Shaft III, during which the mine director received official confirmation of the completion of the task. 

- This project, which has been ongoing for several years, was one of the most important tasks in Pniówek. The most difficult stage - deepening the shaft - has been completed, and work is currently underway to reinforce the shaft pipe on the deepened section - said Adam Rozmus, JSW's Vice-President for Technical and Operational Matters.

The project is being carried out by a consortium of companies: Przedsiębiorstwo Budowy Szybów from the JSW Group and PPG Row-Jas.
 

Other news

Rescue operation in Szczygłowice Section

Death of a miner

A worker injured in an accident that occurred yesterday (22 January) at the Knurów-Szczygłowice mine, Szczygłowice Section, died in a hospital in Siemianowice Śląskie. He was a shift foreman who worked at the Szczygłowice Section for 17 years. Since…

Recovery program in JSW Group subsidiaries

JSW S.A.'s Management Board continues its efforts focused on improving the Group's unfavorable liquidity situation. As part of its Strategic Transformation program, the parent company is pursuing a policy of rationalizing costs, among other things. The same policy…

Expansion of the air conditioning station at KWK Budryk

Work is underway at the Budryk mine to launch the expansion of the surface central air conditioning station. The project involves the construction of two new cooling levels that work with the current station. The resulting installation will be one of the most modern not…

Industry needs a stable regulatory environment

On 1 January 2025 Poland assumed the presidency of the EU Council and for the next six months will be responsible for the meetings of the institution's various bodies, setting the tone for political discussion in the EU forum.

Billions for security

In 2024, JSW earmarked more than PLN 1.6 billion for preventive occupational health and safety. That is more than 50 million more than in 2023, when security investments totaled nearly PLN 1.553 billion. Thanks to preventive measures taken and investments made in modern…

First self-rescuers have arrived in Szczygłowice

The first batch of state-of-the-art Drager BG ProAir self-rescuers purchased by the company last November has arrived at Jastrzębska Spółka Węglowa.

More news