Ikona BIP Ikona Portal Pracownika Ikona poczty Facebook Twitter Instagram Youtube Linkedin RSS Ikona szukania PLEN

Rescue workers at KWK Pniówek return for the last missing miner

Today at 6 p.m. in the Pniówek mine, the next stage of the search for the last of the 7 miners missing in the 20 April 2022 disaster will begin.

photo: Dawid Lach

The rescue operation will start with work to connect the newly excavated cross-cut (N-6a) to the N-6 longwall at the location where the missing miner is believed to be. 

The new N-6a cross-cut, which was excavated from the N-9 ramp towards the N-6 longwall, is nearly 43 meters long. To connect to the longwall, rescue workers must excavate 5 more meters, then they will construct the crossing of the working and the longwall to safely begin ventilation and then penetration of the working.

At the beginning of the operation the penetration may be difficult, as mine management expects an inundated area in the longwall, which may be about 15 meters long.

If the depth of the water does not allow the operation to proceed safely, rescue workers will start to pump it out. Once the water table has reached a safe level, rescue workers will return to the search for the missing miner.

The operation management assumes that on each shift, up to 7 rescue teams from JSW mines and the Central Mining Rescue Station (CSRG) in Bytom will take part in the operation.

 

 


During the rescue operation conducted from 9 to 13 September 2023, the bodies of 6 missing miners were found. After penetrating 185 meters of the N-6 longwall, rescue workers failed to find the last missing miner. Rescue workers were working in increasingly difficult temperature conditions with each meter of progress. The operation manager, after consulting with the extended operation management team, decided to abort the rescue operation due to the safety of the rescue workers.

The mine's management has returned to the second planned solution in the operation plan, i.e. to seal off the longwall area and make a cross-cut (N-6a) from the N-9 ramp directly to the N-6 longwall to the place where the missing miner is likely to be. 

 


The Pniówek mine disaster occurred on 20 April 2022 in longwall N-6, seam 404/4+405/1, 1,000 meters underground, where a quarter past midnight a methane explosion occurred. There were 42 workers in the danger zone. During the operation, 39 workers managed to be evacuated. After 3:00 a.m., a second methane explosion occurred. Seven workers, including a rescue squad, remained in the affected area. A day later, there was another methane explosion. The manager of the rescue operation decided to temporarily seal off the N-6 longwall area, seam 404/4+405/1, with isolation stoppings. The operation was discontinued on 2 May. Of the 10 miners who were taken to the Burn Treatment Center in Siemianowice Śląskie, 5 were in serious condition. In the following days, 5 of the hospitalized miners died. In all, 9 miners lost their lives as a result of the methane explosions, and 7 were then declared missing. 30 people were injured.

Other news

Rescue operation in KWK Pniówek completed

(UPDATE) After seven hours of rescue efforts, rescue workers reached two missing miners with whom contact had been lost after a methane leak in the N-9 working face at a depth of 830 meters. Unfortunately, the doctor pronounced them dead. Both miners were experienced…

Strategic investment in Pniówek completed

December saw the completion of one of the most important investments in the history of the Pniówek mine. The deepening of Shaft III to a depth of 1,053 meters and the commissioning of the new level 1,000 is a landmark stage in improving safety, transport efficiency and…

44th anniversary of the pacification of the Manifest Lipcowy mine

It has been 44 years since the dramatic events that went down in the history of martial law. It was in the Manifest Lipcowy mine—today's Zofiówka—that the first shots were fired at striking miners.

JSW met its production plan for the month of November 2025

Jastrzębska Spółka Węglowa has published the assumptions of the JSW Group's Technical and Economic Plan (TEP) and operating results for November 2025. Coal production exceeded the Plan's targets, but sales were affected by difficult market conditions, which resulted in…

Grand celebrations of St. Barbara's Day

Jastrzębska Spółka Węglowa’s official Barbórka Assembly was held in the “Pniówek” mine. The celebrations began with a prayer and the laying of flowers before the statue of Saint Barbara.

The Minister of Energy repeals the decision to refuse to initiate proceedings concerning JSW’s windfall tax

The Minister of Energy repealed the decision of the Minister of Climate and Environment of 11 June 2025 which refused to initiate proceedings to assert an overpayment and refund of the windfall tax paid by Jastrzębska Spółka Węglowa. The Company published information…

More news