Cooling for the entire mine

Three technological halls, closed-loop water circulation, and an oil-fired boiler room as a backup heat source. These are the features of the air conditioning station which will provide cooling for the Knurów mine workings in the coming months. The performance of the system is equivalent to that of hundreds of air conditioners, and everything is done in an energy-efficient and environmentally friendly way.

photo: Dawid Lach

The station is part of a larger system using methane from the mines to produce electricity and hot water in cogeneration engines. Hot water feeds the systems in the air conditioning station, where it is converted into cooling in the form of chilled water. This ensures that methane is used as efficiently as possible, benefiting both the environment and the economy. The entire system operates in a closed circuit, which reduces water consumption and the amount of process wastewater discharged.

“All station buildings, including connections and chilled water pipelines, were constructed on the surface. The pipelines between the facilities and the desalination plant are also ready. Work is underway to equip the main building with technological installations, ventilation, automation, and electrical systems,” says Grzegorz Musioł, investment department manager at the Knurów-Szczygłowice mine, adding: “Further elements of the system are being installed in the tank and boiler room building. At the same time, work is underway on the development of the site: roads, footpaths, green areas, external sewage systems, and a gas connection to the boiler room are being built.”

Once the project is complete, the station will provide 7.2 MW of cooling power to the mine, with the possibility of expanding to 10.8 MW. 

“Cooling will be produced in cooling units using both absorption chillers (powered by hot water from cogenerators) and compressor chillers. During the winter, the system will utilize natural conditions known as free cooling, which will reduce energy consumption and increase efficiency,” explains Krzysztof Krzemień, deputy head of the ventilation department at the Knurów Section.

Equipment and installations for trial runs are currently being prepared. The entire project is scheduled for completion in August 2026. It will then be possible to start producing and transporting chilled water to underground mining areas.

Central air conditioning will support accessing high-quality coking coal, enabling safe mining of deep seams, increased production, stable working conditions, and long-term development of the mine in the coming years of mining operations.
 

A complex of three technological halls will provide cooling for the entire mine.
Work is currently underway around the station to develop the site.
The station will enable the transmission of 7.2 MW of cooling power to the mine.
The entire system will operate in a closed circuit, which will reduce water consumption.
Preparations for trial runs are underway. This is the final stage before the system is launched.

Other news

Open letter to Representative Trade Union Organizations operating at JSW SA

Dear Sirs/Madams,

On Tuesday, 30 December, another round of talks took place. Unfortunately, it has still not been possible to reach an agreement between the Management Board and the trade unions. We strongly urge you once again to be open to reaching a compromise and…

Talks between the JSW SA Management Board and the trade unions without agreement

(UPTADE) The talks between the JSW SA Management Board and the trade unions concerning the need to temporarily reduce labor costs in the Company ended without reaching an agreement. The JSW SA Management Board remains determined to continue the dialogue and work out…

Rescue operation in KWK Pniówek completed

(UPDATE) After seven hours of rescue efforts, rescue workers reached two missing miners with whom contact had been lost after a methane leak in the N-9 working face at a depth of 830 meters. Unfortunately, the doctor pronounced them dead. Both miners were experienced…

Strategic investment in Pniówek completed

December saw the completion of one of the most important investments in the history of the Pniówek mine. The deepening of Shaft III to a depth of 1,053 meters and the commissioning of the new level 1,000 is a landmark stage in improving safety, transport efficiency and…

44th anniversary of the pacification of the Manifest Lipcowy mine

It has been 44 years since the dramatic events that went down in the history of martial law. It was in the Manifest Lipcowy mine—today's Zofiówka—that the first shots were fired at striking miners.

JSW met its production plan for the month of November 2025

Jastrzębska Spółka Węglowa has published the assumptions of the JSW Group's Technical and Economic Plan (TEP) and operating results for November 2025. Coal production exceeded the Plan's targets, but sales were affected by difficult market conditions, which resulted in…

More news