Cooling for the entire mine

Three technological halls, closed-loop water circulation, and an oil-fired boiler room as a backup heat source. These are the features of the air conditioning station which will provide cooling for the Knurów mine workings in the coming months. The performance of the system is equivalent to that of hundreds of air conditioners, and everything is done in an energy-efficient and environmentally friendly way.

photo: Dawid Lach

The station is part of a larger system using methane from the mines to produce electricity and hot water in cogeneration engines. Hot water feeds the systems in the air conditioning station, where it is converted into cooling in the form of chilled water. This ensures that methane is used as efficiently as possible, benefiting both the environment and the economy. The entire system operates in a closed circuit, which reduces water consumption and the amount of process wastewater discharged.

“All station buildings, including connections and chilled water pipelines, were constructed on the surface. The pipelines between the facilities and the desalination plant are also ready. Work is underway to equip the main building with technological installations, ventilation, automation, and electrical systems,” says Grzegorz Musioł, investment department manager at the Knurów-Szczygłowice mine, adding: “Further elements of the system are being installed in the tank and boiler room building. At the same time, work is underway on the development of the site: roads, footpaths, green areas, external sewage systems, and a gas connection to the boiler room are being built.”

Once the project is complete, the station will provide 7.2 MW of cooling power to the mine, with the possibility of expanding to 10.8 MW. 

“Cooling will be produced in cooling units using both absorption chillers (powered by hot water from cogenerators) and compressor chillers. During the winter, the system will utilize natural conditions known as free cooling, which will reduce energy consumption and increase efficiency,” explains Krzysztof Krzemień, deputy head of the ventilation department at the Knurów Section.

Equipment and installations for trial runs are currently being prepared. The entire project is scheduled for completion in August 2026. It will then be possible to start producing and transporting chilled water to underground mining areas.

Central air conditioning will support accessing high-quality coking coal, enabling safe mining of deep seams, increased production, stable working conditions, and long-term development of the mine in the coming years of mining operations.
 

Other news

JSW increases coal and coke production in Q3

In Q3 2026, the Jastrzębska Spółka Węglowa Group produced 3.31 million tons of coal and 0.74 million tons of coke. Compared to the previous quarter, coal production increased by 2.7 percent and coke production by 10.6 percent.

Results of the 13th edition of the JSW OHS Competition announced. The winner is Marcin Kubicki

240 employees, nine months of competition and challenging questions on occupational health and safety. On 30 September, the 13th edition of the “Internet Competition of OHS Knowledge,” organized by Jastrzębska Spółka Węglowa SA, came to a close. The winner of this…

JSW Group’s financial results for H1 2026

The JSW Group ended the first half of 2026 with a net loss of PLN 1.04 billion, less than half the amount recorded in the corresponding period of last year. In Q2, the Group’s net loss totaled PLN 427.5 million, compared with a loss of PLN 615.9 million recorded in the…

JSW adopts the Remedy Program for 2026-2035

The Remedy Program is intended to ensure the JSW Group’s long-term improvement in profitability, financial liquidity and the alignment of its scale of operations with market and operational conditions. It includes both measures to stabilize the financial standing in the…

Internet broadcast of the results of the JSW Capital Group for the H1 of 2026 year

The Management Board of Jastrzębska Spółka Węglowa S.A. has the pleasure of inviting you to watch the Internet broadcast of the financial results of the JSW Group for the H1 of 2026 year which will take place on September 30, 2026 (Wednesday) at 10:00 (CET).

JSW appoints Vice-President of the Management Board for Financial Matters

The Supervisory Board of Jastrzębska Spółka Węglowa adopted a resolution appointing Bartosz Styś as Vice-President of the JSW Management Board for Financial Matters for the 12th term of office.

More news