Cooling for the entire mine

Three technological halls, closed-loop water circulation, and an oil-fired boiler room as a backup heat source. These are the features of the air conditioning station which will provide cooling for the Knurów mine workings in the coming months. The performance of the system is equivalent to that of hundreds of air conditioners, and everything is done in an energy-efficient and environmentally friendly way.

photo: Dawid Lach

The station is part of a larger system using methane from the mines to produce electricity and hot water in cogeneration engines. Hot water feeds the systems in the air conditioning station, where it is converted into cooling in the form of chilled water. This ensures that methane is used as efficiently as possible, benefiting both the environment and the economy. The entire system operates in a closed circuit, which reduces water consumption and the amount of process wastewater discharged.

“All station buildings, including connections and chilled water pipelines, were constructed on the surface. The pipelines between the facilities and the desalination plant are also ready. Work is underway to equip the main building with technological installations, ventilation, automation, and electrical systems,” says Grzegorz Musioł, investment department manager at the Knurów-Szczygłowice mine, adding: “Further elements of the system are being installed in the tank and boiler room building. At the same time, work is underway on the development of the site: roads, footpaths, green areas, external sewage systems, and a gas connection to the boiler room are being built.”

Once the project is complete, the station will provide 7.2 MW of cooling power to the mine, with the possibility of expanding to 10.8 MW. 

“Cooling will be produced in cooling units using both absorption chillers (powered by hot water from cogenerators) and compressor chillers. During the winter, the system will utilize natural conditions known as free cooling, which will reduce energy consumption and increase efficiency,” explains Krzysztof Krzemień, deputy head of the ventilation department at the Knurów Section.

Equipment and installations for trial runs are currently being prepared. The entire project is scheduled for completion in August 2026. It will then be possible to start producing and transporting chilled water to underground mining areas.

Central air conditioning will support accessing high-quality coking coal, enabling safe mining of deep seams, increased production, stable working conditions, and long-term development of the mine in the coming years of mining operations.
 

Other news

46th anniversary of the Jastrzębie Agreement

Representatives of the JSW Management Board laid flowers in front of the monument commemorating the 46th Anniversary of the signing of the Jastrzębie Agreement. The agreement with the then authorities was concluded on 3 September 1980 in the former Manifest Lipcowy…

JSW's safety net program is proceeding as planned

More than 2,000 employees of Jastrzębska Spółka Węglowa have already taken advantage of mining leave and leave for coal preparation plant employees, and 668 people have opted for one-off cash severance pays. The safety net program at JSW is proceeding according to the…

The end of Jas-Mos

Another chapter in the history of the Jas-Mos mine has come to a close. The JAS II skip shaft tower was demolished using 50 kg of dynamite placed in more than 800 holes drilled into the structure. These are the final cleanup operations at the site, which for years was…

JSW to apply for a loan

On 17 August 2026, the Management Board of Jastrzębska Spółka Węglowa SA adopted a resolution approving the submission of an application to Agencja Rozwoju Przemysłu SA (ARP) for a loan of up to PLN 1.066 billion. The planned financing would replace the ongoing sale of…

JSW with a loan of more than 824 million zlotys

Jastrzębska Spółka Węglowa SA has signed an agreement with the Industrial Development Agency (ARP) regarding a loan under the amended Act on the System of Development Institutions. The total funding amounts to PLN 824 million, and the funds will be disbursed in…

JSW Group’s operational data for Q2 2026

In Q2 2026, the JSW Group reported stable production and higher sales prices, and achieved nearly half of its annual production target.

More news