Cooling for the entire mine

Three technological halls, closed-loop water circulation, and an oil-fired boiler room as a backup heat source. These are the features of the air conditioning station which will provide cooling for the Knurów mine workings in the coming months. The performance of the system is equivalent to that of hundreds of air conditioners, and everything is done in an energy-efficient and environmentally friendly way.

photo: Dawid Lach

The station is part of a larger system using methane from the mines to produce electricity and hot water in cogeneration engines. Hot water feeds the systems in the air conditioning station, where it is converted into cooling in the form of chilled water. This ensures that methane is used as efficiently as possible, benefiting both the environment and the economy. The entire system operates in a closed circuit, which reduces water consumption and the amount of process wastewater discharged.

“All station buildings, including connections and chilled water pipelines, were constructed on the surface. The pipelines between the facilities and the desalination plant are also ready. Work is underway to equip the main building with technological installations, ventilation, automation, and electrical systems,” says Grzegorz Musioł, investment department manager at the Knurów-Szczygłowice mine, adding: “Further elements of the system are being installed in the tank and boiler room building. At the same time, work is underway on the development of the site: roads, footpaths, green areas, external sewage systems, and a gas connection to the boiler room are being built.”

Once the project is complete, the station will provide 7.2 MW of cooling power to the mine, with the possibility of expanding to 10.8 MW. 

“Cooling will be produced in cooling units using both absorption chillers (powered by hot water from cogenerators) and compressor chillers. During the winter, the system will utilize natural conditions known as free cooling, which will reduce energy consumption and increase efficiency,” explains Krzysztof Krzemień, deputy head of the ventilation department at the Knurów Section.

Equipment and installations for trial runs are currently being prepared. The entire project is scheduled for completion in August 2026. It will then be possible to start producing and transporting chilled water to underground mining areas.

Central air conditioning will support accessing high-quality coking coal, enabling safe mining of deep seams, increased production, stable working conditions, and long-term development of the mine in the coming years of mining operations.
 

A complex of three technological halls will provide cooling for the entire mine.
Work is currently underway around the station to develop the site.
The station will enable the transmission of 7.2 MW of cooling power to the mine.
The entire system will operate in a closed circuit, which will reduce water consumption.
Preparations for trial runs are underway. This is the final stage before the system is launched.

Other news

Memorandum of Agreement signed at JSW S.A.

Today (13 February), the Management Board of JSW S.A., together with the Representative Trade Unions and with the participation of Deputy Minister of State Assets Grzegorz Wrona, signed a Memorandum of Agreement on adjusting labor costs to the Company's current…

The result of the referendum at JSW S.A.

In the referendum that ended today, JSW S.A. employees voted in favor of adopting the Suspension Memorandum of Agreement.

Savings at JSW also at the level of Management and Supervisory Boards

Due to the difficult financial standing of JSW, the members of the Company's Management Board will request a reduction in their salaries so that it is adjusted to the Company's current financial situation.

Announcement by the Ministry of State Assets

For many months, the management of the Ministry of State Assets has been consistently taking steps to develop an optimal remedy plan for Jastrzębska Spółka Węglowa, which is in a very difficult financial position.

JSW has obtained approval from the Social Insurance Institution (ZUS) to pay contributions in installments

Jastrzębska Spółka Węglowa has received approval from the Social Insurance Institution to pay part of its contribution liabilities in installments.

A referendum on the Draft Suspension Memorandum of Agreement to be held at JSW

Jastrzębska Spółka Węglowa S.A. announces the completion of negotiations and agreement on the terms and conditions for the Draft Suspension Memorandum of Agreement. The Memorandum of Agreement will aim to introduce temporary changes to the terms and conditions of…

More news