Ikona BIP Ikona Portal Pracownika Ikona poczty Facebook Twitter Instagram Youtube Linkedin RSS Ikona szukania PLEN

Shaft sinking completed at Zofiówka

The sinking of shaft IIz to a depth of 1,104.68 meters has been completed at the Borynia-Zofiówka-Bzie mine in the Zofiówka Section. This is a very important project for the mine from the point of view of building the new 1,080 level.

photos: Michał Kaczorek

A ceremony was held on Wednesday (23 April) at the bottom of the completed shaft IIz, during which the mine director received a report from the contractor, officially confirming the completion of the task. 

- The main functions that the shaft will perform are the transportation of people and materials to level 1,080 by the southern compartment and the improvement of ventilation conditions at the newly built level - said Łukasz Szlązak, director of the Borynia-Zofiówka-Bzie mine.

The sinking of shaft IIz in the Zofiówka Section from a depth of 929.5m began in April 2017. Initially, the work was carried out through a consortium of Elektrometal (leader), Budwak and KPRGiBSz. In April 2022, the consortium leader, due to the bankruptcy proceedings of the consortium members, further work was contracted to Przedsiębiorstwo Budowy Szybów, which is part of the JSW SA Group. 

- In the mines of Jastrzębska Spółka Węglowa, we have been going lower and lower with mining for several years. Almost all mines have new levels under construction, so in order to ensure better ventilation of the levels under construction and transport of people and materials, we have to deepen the shafts. Shaft IIz in the Zofiówka Section is an example of consistent implementation of the adopted plans - says Adam Rozmus - Vice-President of the JSW for Technical and Operational Matters.

Currently, the shaft is sunk to a depth of 1,104.68 m, constructed in a final casing with a double-sided inlet at the 1,080 m level and single-sided inlets at depths of 1,058.03 m and 1,099.68 m.

Other news

The end of Jas-Mos

Another chapter in the history of the Jas-Mos mine has come to a close. The JAS II skip shaft tower was demolished using 50 kg of dynamite placed in more than 800 holes drilled into the structure. These are the final cleanup operations at the site, which for years was…

JSW to apply for a loan

On 17 August 2026, the Management Board of Jastrzębska Spółka Węglowa SA adopted a resolution approving the submission of an application to Agencja Rozwoju Przemysłu SA (ARP) for a loan of up to PLN 1.066 billion. The planned financing would replace the ongoing sale of…

JSW with a loan of more than 824 million zlotys

Jastrzębska Spółka Węglowa SA has signed an agreement with the Industrial Development Agency (ARP) regarding a loan under the amended Act on the System of Development Institutions. The total funding amounts to PLN 824 million, and the funds will be disbursed in…

JSW Group’s operational data for Q2 2026

In Q2 2026, the JSW Group reported stable production and higher sales prices, and achieved nearly half of its annual production target.

First employees to take mining leave at JSW

On 1 July 2026, at Jastrzębska Spółka Węglowa, the first group – 1,123 employees – took advantage of the program offering mining leave, which was launched following the signing of a subsidy agreement between JSW and the Ministry of Energy.

A subsidy agreement for mining and processing leave at JSW has been signed

Jastrzębska Spółka Węglowa SA has signed a subsidy agreement with the Ministry of Energy regarding the financing of employees taking mining leave and leave for coal preparation plant employees. It is projected that in 2026, 3,092 JSW workers will take the leave. The…

More news