Return of the plough

After a four-year break the Pniówek mine again launched a longwall mined using the plough technology.

photo: Rafał Bilat

The PW -1 plough longwall in seam 358/1 has the initial strike of 720 meters and the length of 200 meters. The coal is mined in a seam with the thickness ranging from 1 to 1.4 meters. In the longwall we employ miners from the G-3 unit who have experience in operating plough longwalls  – says Marek Malcharek, mining work manager responsible for operations in KWK Pniówek.  

For the time being, the longwall is at the commissioning stage, but the target daily progress is planned to be in the range of 8.2 meters, with the daily output of 3 thousand tons of coal.  

The longwall shearer comprising: the GH9-38/VE plough, JZR-11/25 mechanized roof support sections and PF4/932 face conveyor, supports operation of seams with the thickness from 1 to 1.7 meters. The plough head may have a cut of as much as 21 centimeters, working at the speed of 1.9 meters per second. Such fast daily progress of the longwall front requires efficient preparation of longwall roadways.

We should remember that a plough longwall is nearly fully automated and controlled using the control panel located in the longwall roadway. The staffing of the longwall is limited to the absolute minimum and amounts to 3-4 miners. In a longwall mined in the traditional way 12 people have to be employed. Unfortunately a plough has its drawbacks. With such a fast progress, more miners in the longwall bays are required. The mining of the PW-1 longwall is planned to be closed by mid-March 2020. – After we finish to mine the PW-1 longwall we plan to use the plough complex in further four longwalls with low seams– say Malcharek.

 

Other news

Coking coal at the center of industrial transition

During the 17th European Economic Congress in Katowice, Adam Rozmus, Vice-President of the JSW Management Board for Technical and Operational Matters, spoke in a debate on the future of the mining industry. Panelists discussed, among other things, the place of coking…

Shaft sinking completed at Zofiówka

The sinking of shaft IIz to a depth of 1,104.68 meters has been completed at the Borynia-Zofiówka-Bzie mine in the Zofiówka Section. This is a very important project for the mine from the point of view of building the new 1,080 level.

Polish Cup returns to JSW Jastrzębski Węgiel

After a 15-year hiatus, the volleyball players once again took the TAURON Polish Cup, defeating Aluron CMC Warta Zawiercie 3:1 in the final in Kraków. After the great success, the team appeared with the trophy at the headquarters of JSW, the title sponsor, where they…

JSW SA has applied to the Ministry of Climate and Environment for a refund of the windfall tax

On Friday, 11 April 2025, JSW SA requested a refund of the windfall tax of PLN 1.6 billion paid in 2023 and surcharged in 2024. This is the result of a thorough analysis of the regulations that imposed the obligation to pay this levy on the Company.

Budryk Mine hosted the best students of mining schools

Promoting a culture of safety among young people, educating about labor law and OHS principles, as well as drawing attention to the importance of mining for the region and the economy - these are the main goals of the competition entitled "Safe Step to Mining with OHS",…

New longwalls in Pniówek mine

Two new longwalls with total reserves of approx. 1.4 million tons of coking coal with very good parameters have been put into operation at the Pniówek mine.