The construction of the shaft in Bzie

Shaft sinking in Bzie was officially completed on Monday October 10, 2016. At the depth of 1,164 meters, at the bottom of the shaft, Józef Pawlinów, JSW Vice - President for Technical Matters and Janusz Olszewski, Vice- President of Kopex board PBSz received, according to the tradition of mining, a report of completion of the work.

photo: Dawid Lach

-Shaft I Bzie is a guarantee of Borynia- Zofiówka-Jastrzębie mine and JSW development. A new shaft will allow us to reach some of the largest deposits of coking coal in Europe - said Józef Pawlinów, Vice- President of JSW. 

Agreement on the shaft sinking  was signed in 2009 and in December 2010 the drilling began. JSW paid for the investment over PLN300 million, while the cost of Bzie 1 sinking  amounted to about 250 million.

- It was the first shaft sunk since more than twenty years in Silesia. We are pleased that together with  Jastrzębska Spółka Węglowa we were able to bring the investment to a successful end - said Janusz Olszewski,Vice- President of Kopex PBSz.

Shaft 1 Bzie will allow us to reach some of the largest deposits of coking coal type hard 35.2 in Europe - Bzie-Dębina 2-West and Bzie-Debina 1-West. The size of balance resources occurring in these deposits is estimated at over 300 million tones. Thanks to the access to deposits, Borynia- Zofiówka-Jastrzębie mine longevity and development will be extended at least until the year 2051. Shaft 1 Bzie is already connected to the excavations of Zofiówka Site at the level 1110. Thanks to this,  Zofiówka Site gained the necessary ventilation which will allow to carry out preparatory work smoothly and especially operating works in the seam N 505/1, which in 2018 is expected to start operation of the first wall.

Other news

Coking coal at the center of industrial transition

During the 17th European Economic Congress in Katowice, Adam Rozmus, Vice-President of the JSW Management Board for Technical and Operational Matters, spoke in a debate on the future of the mining industry. Panelists discussed, among other things, the place of coking…

Shaft sinking completed at Zofiówka

The sinking of shaft IIz to a depth of 1,104.68 meters has been completed at the Borynia-Zofiówka-Bzie mine in the Zofiówka Section. This is a very important project for the mine from the point of view of building the new 1,080 level.

Polish Cup returns to JSW Jastrzębski Węgiel

After a 15-year hiatus, the volleyball players once again took the TAURON Polish Cup, defeating Aluron CMC Warta Zawiercie 3:1 in the final in Kraków. After the great success, the team appeared with the trophy at the headquarters of JSW, the title sponsor, where they…

JSW SA has applied to the Ministry of Climate and Environment for a refund of the windfall tax

On Friday, 11 April 2025, JSW SA requested a refund of the windfall tax of PLN 1.6 billion paid in 2023 and surcharged in 2024. This is the result of a thorough analysis of the regulations that imposed the obligation to pay this levy on the Company.

Budryk Mine hosted the best students of mining schools

Promoting a culture of safety among young people, educating about labor law and OHS principles, as well as drawing attention to the importance of mining for the region and the economy - these are the main goals of the competition entitled "Safe Step to Mining with OHS",…

New longwalls in Pniówek mine

Two new longwalls with total reserves of approx. 1.4 million tons of coking coal with very good parameters have been put into operation at the Pniówek mine.

More news