Ikona BIP Ikona Portal Pracownika Ikona poczty Facebook Twitter Instagram Youtube Linkedin RSS Ikona szukania PLEN

Replacement of pulley wheels after 51 years of operation

After half a century of uninterrupted service, it was time to replace the pulley wheels on shaft III at the Pniówek mine. This complex logistical and technical operation required great precision.

photos: Krzysztof Barteczko

The pulley wheels of Shaft III's West compartment have handled miner traffic and material transport for 51 years, since the mine's inception. Now, after five decades of heavy use, they have been replaced with new ones. The decision to replace them was made together with the mine's operations expert following specialized tests.

A set of top upper pulley wheels with the diameter of 4,000 mm each and weighing a total of 10 tons first had to be dismantled and then safely lowered to the ground. A specialized crane then transported the new components to the shaft tower, which were subsequently mounted after many hours of precision work. All this took place at an altitude of 50 meters.

- In order to replace the set of upper pulley wheels, we had to relieve the entire system to loosen and remove two 40 mm diameter hoisting support ropes. Due to the weight of the set of wheels and the height to which they had to be lifted we hired a specialized crane for the work. The proper alignment of the wheels on the tower was determined and confirmed by the surveying services of our mine - explains Sebastian Berger, chief underground energy and mechanical engineer at the Pniówek mine. 

The most important thing is that the whole thing was carried out by the mine's crew, i.e. experienced employees of the Pniówek mine's shaft crews. Instead of using third party companies, they relied on the knowledge and practice of the people who know the mine best. 

- For all employees involved in this modernization, this was very challenging but also rewarding. The excellent skills of our employees made it possible to carry out this very difficult task efficiently - said Zbigniew Czarnecki, director of the Pniówek mine.

Thanks to the commitment of the shaft crews and the good organization of work under the guidance of experienced senior supervisors, all tasks were carried out efficiently, safely and according to plan.

Other news

"A modern economy starts with mining"

This slogan was repeated many times during the three days of debates on raw materials, modern technologies and the future of industrial Silesia. The three-day Future Mining Forum & Expo conference, which brought together representatives from the mining sector, industry,…

46th anniversary of the Jastrzębie Agreement

Representatives of the JSW Management Board laid flowers in front of the monument commemorating the 46th Anniversary of the signing of the Jastrzębie Agreement. The agreement with the then authorities was concluded on 3 September 1980 in the former Manifest Lipcowy…

JSW's safety net program is proceeding as planned

More than 2,000 employees of Jastrzębska Spółka Węglowa have already taken advantage of mining leave and leave for coal preparation plant employees, and 668 people have opted for one-off cash severance pays. The safety net program at JSW is proceeding according to the…

The end of Jas-Mos

Another chapter in the history of the Jas-Mos mine has come to a close. The JAS II skip shaft tower was demolished using 50 kg of dynamite placed in more than 800 holes drilled into the structure. These are the final cleanup operations at the site, which for years was…

JSW to apply for a loan

On 17 August 2026, the Management Board of Jastrzębska Spółka Węglowa SA adopted a resolution approving the submission of an application to Agencja Rozwoju Przemysłu SA (ARP) for a loan of up to PLN 1.066 billion. The planned financing would replace the ongoing sale of…

JSW with a loan of more than 824 million zlotys

Jastrzębska Spółka Węglowa SA has signed an agreement with the Industrial Development Agency (ARP) regarding a loan under the amended Act on the System of Development Institutions. The total funding amounts to PLN 824 million, and the funds will be disbursed in…

More news