April brought tangible effects of the Strategic Transformation Plan at JSW

Jastrzębska Spółka Węglowa has been consistently executing its Strategic Transformation Plan (PST), implemented since December 2024. April was another month of intense activity in key areas - production and costs.

photo: Dawid Lach

 The most advanced work has been seen in the "Efficient Mine" workstream, which has launched a pilot program to increase mining production. It has been implemented at five selected longwalls - at the Pniówek and Budryk mines, as well as the Knurów, Borynia and Zofiówka Sections. In addition to previously developed technical solutions, among other things, a modified incentive system for longwall crews has been applied. 

The results were very promising - in April, production at the longwalls included in the pilot program amounted to 325,000 net tons of coal, up 17 percent from the planned 278,000 tons.

The pilot is continuing in May, and has been further rolled out to selected working faces, with a view to speeding up development work. 

“I am positive about the effects of the pilot, so from June we intend to roll it out to include longwalls and working faces where geological and mining conditions allow us to accelerate work without adversely affecting the safety of the work. We are talking about approx. 75% of the longwalls. Meanwhile, starting in July, further changes will be implemented, this time in auxiliary functions that have a direct impact on production level," explains Ryszard Janta, President of the JSW Management Board, and adds: “Only consistent and coherent implementation of the PST based on the competence and commitment of our employees will allow the Company to come out on top and achieve long-term profits.”

In addition to increasing production, there are also cost-saving projects underway at JSW. In the area of procurement, PST activities have yielded tangible savings of more than PLN 307 million as of 22 May, which is 85 percent of the target amount for 2025. In the case of investments, savings of more than PLN 1.2 billion have already been achieved. Work is currently underway to optimize expenditures on longwall outfitting, expensable mining pits and optimize other capital expenditures.

Parallel to the activities carried out at JSW, the PST also includes projects at JSW Group companies aimed at improving the efficiency of the entire Group.

Other news

JSW appoints Vice-President of the Management Board for Financial Matters

The Supervisory Board of Jastrzębska Spółka Węglowa adopted a resolution appointing Bartosz Styś as Vice-President of the JSW Management Board for Financial Matters for the 12th term of office.

"A modern economy starts with mining"

This slogan was repeated many times during the three days of debates on raw materials, modern technologies and the future of industrial Silesia. The three-day Future Mining Forum & Expo conference, which brought together representatives from the mining sector, industry,…

JSW updates its Technical and Economic Plan for 2026

Jastrzębska Spółka Węglowa has updated its Technical and Economic Plan for 2026. The Company expects to produce 13.3 million tons of coal, including over 11.2 million tons of coking coal. The Plan also calls for approximately PLN 1.9 billion in capital expenditures at…

46th anniversary of the Jastrzębie Agreement

Representatives of the JSW Management Board laid flowers in front of the monument commemorating the 46th Anniversary of the signing of the Jastrzębie Agreement. The agreement with the then authorities was concluded on 3 September 1980 in the former Manifest Lipcowy…

JSW's safety net program is proceeding as planned

More than 2,000 employees of Jastrzębska Spółka Węglowa have already taken advantage of mining leave and leave for coal preparation plant employees, and 668 people have opted for one-off cash severance pays. The safety net program at JSW is proceeding according to the…

The end of Jas-Mos

Another chapter in the history of the Jas-Mos mine has come to a close. The JAS II skip shaft tower was demolished using 50 kg of dynamite placed in more than 800 holes drilled into the structure. These are the final cleanup operations at the site, which for years was…

More news