The construction of the shaft in Bzie

Shaft sinking in Bzie was officially completed on Monday October 10, 2016. At the depth of 1,164 meters, at the bottom of the shaft, Józef Pawlinów, JSW Vice - President for Technical Matters and Janusz Olszewski, Vice- President of Kopex board PBSz received, according to the tradition of mining, a report of completion of the work.

photo: Dawid Lach

-Shaft I Bzie is a guarantee of Borynia- Zofiówka-Jastrzębie mine and JSW development. A new shaft will allow us to reach some of the largest deposits of coking coal in Europe - said Józef Pawlinów, Vice- President of JSW. 

Agreement on the shaft sinking  was signed in 2009 and in December 2010 the drilling began. JSW paid for the investment over PLN300 million, while the cost of Bzie 1 sinking  amounted to about 250 million.

- It was the first shaft sunk since more than twenty years in Silesia. We are pleased that together with  Jastrzębska Spółka Węglowa we were able to bring the investment to a successful end - said Janusz Olszewski,Vice- President of Kopex PBSz.

Shaft 1 Bzie will allow us to reach some of the largest deposits of coking coal type hard 35.2 in Europe - Bzie-Dębina 2-West and Bzie-Debina 1-West. The size of balance resources occurring in these deposits is estimated at over 300 million tones. Thanks to the access to deposits, Borynia- Zofiówka-Jastrzębie mine longevity and development will be extended at least until the year 2051. Shaft 1 Bzie is already connected to the excavations of Zofiówka Site at the level 1110. Thanks to this,  Zofiówka Site gained the necessary ventilation which will allow to carry out preparatory work smoothly and especially operating works in the seam N 505/1, which in 2018 is expected to start operation of the first wall.

Other news

JSW Group reports earnings of nearly one billion PLN

A drop in raw material prices, higher production costs and a windfall tax of PLN 1.6 billion (imposed on us as the only company in Poland) affected the Company's financial results. Despite this, the JSW Group closed the previous year with a net profit of almost PLN 1…

Anniversary of the Pniówek mine disaster

Two years have passed since the biggest disaster in the history of Jastrzębska Spółka Węglowa and the Polish mining industry. On 20 April 2022, 16 miners and rescue workers lost their lives in the Pniówek mine.

Internet broadcast of the results of the JSW Capital Group for the 2023 year

The Management Board of Jastrzębska Spółka Węglowa S.A. has the pleasure of inviting you to watch the Internet broadcast of the financial results of the JSW Group for the 2023 year which will take place on April 24, 2024 (Wednesday) at 9:00 (CET)

Aktualności JSW SANew composition of the JSW Management Board

Ryszard Janta has been elected by the JSW Supervisory Board as President of the Jastrzębska Spółka Węglowa Management Board. He will assume his post on 30 April 2024. In parallel, Mr. Janta will perform the duties of Vice-President for Development until 6 May 2024.

There will be more coking coal from KWK Budryk

The second stage of modernization of the coal preparation plant has begun at the Budryk mine. After the work is completed, the mine's coking coal production will increase to 95 percent. The Budryk mine’s coal preparation plant is already one of the most modern in the…

Aktualności JSW SACompetitions with no resolution

The Supervisory Board of Jastrzębska Spółka Węglowa SA completed the recruitment procedure for the positions of President of the JSW SA Management Board, Vice-President of the Management Board for Financial Matters and Vice-President of the Management Board for…

More news