The injured miners are now home

The two miners injured in the accident on Saturday left the hospital today. The intensive rescue operation continues underground.

During the drilling of the borehole through which a microphone, among other things, was dropped this morning, we ran into water in the rock mass. The head of the rescue operation decided to lay cement there so that water would not flow into it and so the surface of the flooded area would not rise.

To enhance the efficiency of the compressed air pumps operating there, one electric pump will also be put to use. It will be installed at the end of the overall system. This 900 kg device is being transported in the roadway in three parts (frame, engine and pump). The weight and dimensions (2 meters long and 75 cm high and wide) of the pump and the limited headroom in the roadway are hindering its transport. The water from the flooded area will be pumped out using a cascade of 3 or 4 pumps. The efficiency will be 7 times greater when using a powerful electrical device.

The electric pump has been ready for operation for several days. However, until now its use was not possible because the methane concentration was too high. Electrical devices can operate in a mining pit provided the methane concentration does not exceed 2%.

Krzysztof Tchórzewski, Minister of Energy and Grzegorz Tobiszowski, Deputy Minister arrived at the Zofiówka Section today. They participated in the meeting of the crisis management team and they talked with the rescue workers. Minister Tchórzewski also met with the miners’ families.

Other news

Aktualności JSW SACompetitions with no resolution

The Supervisory Board of Jastrzębska Spółka Węglowa SA completed the recruitment procedure for the positions of President of the JSW SA Management Board, Vice-President of the Management Board for Financial Matters and Vice-President of the Management Board for…

JSW with loan for battery-powered locomotives

Eight VOLTER overhead battery-powered locomotives with complete transport sets have been delivered to the Budryk mine in Ornontowice. The investment was made thanks to a PLN 9.96 million loan from the Voivodeship Fund for Environmental Protection and Water Management in…

Aktualności JSW SACompetition for two positions on the JSW SA management board has been resolved

On Thursday, 14 March, JSW's Supervisory Board dismissed from the Company's Management Board: Edward Paździorko, Vice-President of the Management Board for Technical and Operational Matters. The position will be filled by Adam Rozmus. Additionally, JSW SA’s Supervision…

30 years of the Budryk mine

Before the first ton of coal was extracted from the Budryk mine on 14 March 1994, 15 years had passed since the start of the construction. Governments changed, political systems in Eastern Europe changed and new states were created, borders changed, and the construction…

Gala celebration in the AGH auditorium to mark the 30th anniversary of coal mining at the Budryk mine

- The AGH University of Science and Technology started 105 years ago as a mining university preparing personnel for the mining industry in the reborn Poland, which was then the economic and technological basis of the economy. The auditorium of the university is…

JSW met with representatives of the capital market

Jastrzębska Spółka Węglowa, the EU’s largest coking coal producer, attended the 24th Capital Market Conference in Bukowina Tatrzańska, Poland. Every year, this event attracts numerous finance and business professionals. For JSW, the conference served as an excellent…

More news